Metering Standoff: FG, DisCos Trade Blame as 2.5 Million Power Meters Risk Rotting in Warehouses

By Titilope Johnson
Nigeria’s long-running electricity metering crisis has escalated into a fresh institutional standoff, with the Federal Government accusing electricity distribution companies (DisCos) of frustrating free meter installations—an impasse that could leave as many as 2.5 million meters idle in warehouses by the end of 2026.
The meters, procured under the National Mass Metering Programme (NMMP) and the Presidential Power Initiative (PPI) with support from the World Bank and the Federation Account, were designed to shrink Nigeria’s estimated seven-million metering gap and curb the widespread use of estimated billing. However, despite the availability of meters and fully paid installers, deployment has remained sluggish.
The Minister of Power, Adebayo Adelabu, disclosed that only 150,000 meters have been installed out of one million already procured under the Federal Government’s free metering scheme. He warned that without a rapid scale-up in installation, unused meters could balloon to about 2.5 million as new batches arrive.
Although the Federal Government owns about 40 per cent equity in DisCos and is represented on their boards, it has squarely blamed the companies for the delays. Speaking through his Special Adviser on Media, Bolaji Tunji, Adelabu said DisCos have failed to provide accurate customer data and adequate support to installers, effectively stalling deployment.
According to the Ministry of Power, the intervention became necessary after years of underperformance by DisCos, which are legally responsible for metering their customers. Adelabu explained that the government stepped in through the World Bank-funded Distribution Sector Recovery Programme (DISREP) to accelerate progress.
Under the programme, the government secured grants to procure meters directly for consumers, embedding installation costs into the procurement process to ensure households pay nothing. Each meter is configured for a specific DisCo’s franchise area, making cross-deployment impossible. Suppliers have also been fully paid for both meters and installation.
Despite these safeguards, meters are reportedly piling up in DisCos’ warehouses. The minister’s team cited poor enumeration and inaccurate customer information as major bottlenecks, noting that installers are often sent to wrong addresses or to premises not ready for installation. In some cases, only four out of every ten sites surveyed are viable for immediate metering.
Adelabu revealed that fresh meetings are being planned with key stakeholders, including the World Bank, Bureau of Public Enterprises (BPE) and DisCos, to resolve the impasse. With another 1.5 million meters expected under ongoing initiatives such as the Presidential Metering Initiative, the gap between supply and deployment could widen further.
He stressed that the government is prepared to intervene more forcefully— including helping DisCos clean up customer data—insisting that ending estimated billing is non-negotiable under the administration’s power-sector reforms.
Meanwhile, a DisCo operating in Nigeria’s northern region has rejected claims that electricity distributors are deliberately frustrating the programme, blaming poor contractor capacity and weak logistics instead.
A senior official, who spoke on condition of anonymity, said that while 1.4 million meters were contracted nationwide, deliveries to individual DisCos fell short. Of 109,251 meters allocated to the utility, fewer than half were delivered, with about 33,000 already installed and only 16,000 remaining in storage.
The official added that installation had recently improved to about 800 meters daily, but warned that existing stock could be exhausted within a month without fresh deliveries.
Addressing concerns about customer data, the source dismissed claims of poor KYC, blaming instead the appointment of a single installer to cover multiple states with inadequate logistics. Subcontracted installers, the official said, are poorly paid—discouraging thorough pre-installation checks.
In contrast, a southern DisCo denied hoarding meters, stating that the DISREP metering programme had not yet commenced in its region.
A source at the Nigerian Electricity Regulatory Commission (NERC) said some DisCos have delayed installations under the Meter Acquisition Fund, preferring direct cash allocations—an approach that has previously triggered legal disputes.
Energy economist Prof. Adeola Adenikinju said the controversy reflects weak enforcement rather than flawed policy, calling for sanctions against non-compliant DisCos and greater empowerment of third-party installers.
Similarly, Prof. Wunmi Iledare described the situation as a symptom of deeper governance failures, questioning why NERC has been reluctant to impose penalties and warning that estimated billing erodes consumer trust.
Meanwhile, a coalition of civil society groups under the Nigerian Human Rights Community (NHRC) backed Adelabu’s directive that World Bank-funded meters must be installed free of charge, alleging that some DisCos still demand between ₦200,000 and ₦350,000 from consumers.
The group warned it may mobilise mass action against DisCos, while former CIBN President, Prof. Segun Ajibola, urged the government to “wield the big stick,” arguing that resistance to prepaid metering is driven by the loss of arbitrary billing revenues.
As tensions deepen, stakeholders agree on one point: without firm enforcement, clear accountability and stronger regulation, millions of Nigerians may remain trapped under estimated billing—despite warehouses full of unused meters.